Aqua Services & Engineering

![]() |
|
|
| Supply and Installation of 500PE Containerised Sewage Treatment Plant at North Mara Gold Mine, Tarime, Tanzania, for Barrick Africa ASE was selected to provide a new containerised sewage treatment plant to serve the expansion of the site at North Mara Gold Mine, in the north of Tanzania, which necessitated a plant to serve 500 persons staying permanently on site. After preliminary discussions and a visit to site, the complete containerised plant was manufactured at ASE’s facility in Windhoek prior to shipment. The unit consists of four rubber-lined mild steel tanks with a capacity of 35m³ each to serve as septic tanks, in addition to two 40ft containers that house the trickling filter plant, secondary settler and intermediate pumps and control. The plant was constructed in such a way as to minimise the time required on site for installation. |
|
| Plant containers nearing completion |
|
click photos to enlarge |
|
Once completed, the plant components were loaded onto four trucks for transport to site by road. It took 3 weeks for the plant to reach the mine, after which ASE’s installation supervisor travelled to the site to oversee the installation. |
Containers ready for loading
|
ASE entered a team in DTS Pennypinchers 5-a-side soccer tournament on 23rd & 24th October 2009. Although ASE didn’t win any games it was an entertaining tournament and the team enjoyed the "exercise" on the field and afterwards! The idea behind the tournament was to raise money to upgrade the sport field. Here are the scores. TFTM Pimps vs ASE 3:1 DTS Old Boys vs ASE 3:1 OTB Sports 1 vs ASE 2:2 Penny Boys vs ASE 4:0 |
![]() |
![]() |
|
ISO 9001/2008 certification Through this award ASE wishes to ensure and confirms to all clients and the community of Namibia of the highest standard of service for the supply of water treatment equipment, chemicals and instruments. |
|
Goreangab Water Reclamation Plant, Windhoek |
|
Opuwo Nanofiltration Plant MODULAR PACKAGE TREATMENT WORKS: The town of Opuwo obtains its water from several boreholes on the outskirts of the town. However, the raw water is of a very poor quality and not safe to drink. Of primary health concern are high sulphate concentrations (>600 mg/l as SO4) that render the raw water not acceptable for potable consumption. Also, the very high total hardness (>1 150 mg/l as CaCO3) contained in the raw water, besides being a nuisance because it causes excessive scaling in pipes and other water retaining appliances, necessitates a high degree of replacement of pipes and excessive maintenance to the distribution system of the town. ASE installed a membrane filtration plant, using Nano-Filtration (NF) technology, to treat the raw water to obtain a Class A final water. As an initial phase, Phase 1 of the project entails providing 1 000 m³/d of Class A water to Opuwo Town. Further extensions (Phases 2 and 3) to this project are planned and will be incorporated as the demand increases. |
![]() |
| Opuwo Plant building with membrane racks visible | |
![]() |
|
| Nanofiltration Membrane Rack at Opuwo Plant | |
Walvis Bay Municipality |
|
Trickling Filter Plants Aqua Services & Engineering (Pty) Ltd has designed a very efficient biological treatment system making use of septic tank, trickling filter and secondary settler to treat domestic sewage. The process is simple, robust, already proven in Namibia and guarantees a final effluent quality conforming to environmental standards (as presently enforceable by various legislation). Plant Concept
Biological principles
Biological (microbial) attachment Trickling Filter Media The organic material in the wastewater is absorbed onto the biological film. In the outer portion of the film, aerobic organisms degrade the organic material. The organisms obtain their oxygen by natural draught through the filter. As the microorganisms grow, the thickness of the slime layer increases, and the diffused oxygen is consumed before it can penetrate the full depth of the slime layer. An anaerobic environment is thus created near the surface of the media. As the slime layer increases in thickness, the absorbed organic matter is metabolized before it can reach the microorganisms near the surface. As a result of having no external organic source available, the microorganisms near the media surface enter into an endogenous phase of growth and loose their ability to cling to the surface. The liquid then washes off the slime from the media, and new slime layer starts to grow. This phenomenon is called ‘sloughing’ and is primarily a function of the hydraulic and organic loading account for the rate of metabolism in the slime layer. The velocity in modern filters is specifically adjusted to maintain a slime layer of uniform thickness. Advantages of the Trickling Filter System The Trickling Filter Systems show the following advantages over other treatment technologies that produce a high quality of treated effluent:
|
|
LANGSTRAND Part of the envisaged resort developments includes an eco village and greenbelt-area. Therefore, reuse of the final effluent discharged by the sewage works is needed to save precious potable water otherwise required (and not available) to water these plants. |
![]() |
| Plant at Langstrand showing the septic tank, trickling filter, settler and Cl contact tank | |
Being a holiday resort, extreme seasonal fluctuations in sewage volumes and loadings occur. This aspect required specific consideration during the design phase. Attention was given to the following specific points for a new sewage treatment plant for Langstrand:
The above conditions led to the provision of sewage reticulation and a sewage treatment plant based on trickling filter technology. Aqua Services & Engineering (Pty) Ltd was awarded this project on the basis that they provide the complete design, supply and install the mechanical- and electrical equipment, and commission the finished plant. Other contractors appointed by the Client undertook the civil works. |
|
HENTIES BAY Henties Bay is a thriving holiday resort situated along the West Coast of Namibia, ca 80 km north of Swakopmund. Mainly local and South African holidaymakers frequent the town and its infrastructure is subject to huge seasonal fluctuations due to large increases in population during the holiday season. Previously, the main method of sewage disposal to date consisted of septic tanks with soakaways, but due to the large number of residences in this town, this method of sewage disposal was unsatisfactory and could not be tolerated any more. |
![]() |
| Aerial view of plant at Henties Bay, showing space allocated for future expansion | |
One of the main problems was that the ground became saturated, especially during the holiday season, and final effluent from the soakaways then seeped into the sea. Since the town was built on dunes elevated above sea level, the soakaway water also washed out dune sand thereby endangering the stability of the underground on which the houses are built. Also, the soakaway water eventually finds its way onto the beaches and also contaminates the surf, where it poses a serious health hazard and esthetically unpleasant conditions for holidaymakers along the beaches. These unacceptable conditions necessitated urgent sewage reticulation with a proper treatment works and acceptable disposal (or reuse) of the final effluent to be provided for the town. It was therefore decided to provide sewage reticulation and a sewage treatment plant, based on trickling filter technology. The final plant will treat all sewage collected at various points throughout the town and will be constructed in three phases, of which the completion of the first phase is completed and shown above. Aqua Services & Engineering (Pty) Ltd provided the complete design, supply and installation of the mechanical- and electrical equipment, and commissioning of the finished plant. Other contractors appointed by the client undertook the civil works. |
|
SKORPION ZINC MINE The upgrade to the treatment train required was for a capacity of 150 m³/d. Various biological treatment options were considered to treat the raw sewage to a standard acceptable for discharge into the environment and/or for re-use as irrigation water for lawns. From the vast palette of advanced biological treatment technologies available, new generation trickling filter technology was considered most appropriate. Aqua Services & Engineering (Pty) Ltd was awarded this project on the basis that they provided the complete design, supply and install the mechanical- and electrical equipment, and commissioned the finished plant. Other contractors appointed by the client undertook the civil works.
|
![]() |
| Trickling Filter at Skorpion Zinc Mine, final stages of installation | |
KAYELEKERA (MALAWI) The Kayelekera Uranium Project is a new uranium mine that is being developed near the town of Karonga, in the Northern part of Malawi. The project is being managed for the Client, Paladin (Africa) Ltd, by Engineering & Projects Company (EPC). Two sewage treatment plants were required to treat sewage generated at the mine and nearby village. Various biological treatment options were considered to treat the raw sewage to a standard acceptable for discharge into the environment and/or for re-use as irrigation water for lawns. From the vast palette of advanced biological treatment technologies available, new generation trickling filter technology was chosen because it was considered most appropriate for local conditions in Malawi, due to its simple and robust operating principles. Aqua Services & Engineering (Pty) Ltd was awarded this project on the basis that they provided the complete design, supplied mechanical- and electrical equipment, supervised the on-site installation and commissioned the finished plant. |
|
North Mara Gold Mine - Ongoing Project The mining company Barrick Gold Ltd, based in Canada, is reviving their gold-mining activities at the North Mara Gold Mine in northern Tansania. Due to the rapid implementation of the works, ASE was approached to deliver a containerised sewage treatment plant with a capacity of 500 population equivalent, based on trickling filter technology. This was envisaged to be the most suitable solution for the location, as this type of plant is flexible, easily moved, as well as robust and requiring very little maintenance. |
|
Water shortage in Walvisbay They are now busy repairing part of the power line and hopefully by Thursday 5 March they can start more pumps (±200m³/h) The average consumption of Walvisbay is 700m³/h. We also installed a Sodium Hipochloride dosing station at the emergency pump station in Swakopmund that pumps water to Walvisbay. ASE also assists with the truck to support the community with water. The truck fills up at the Fire brigade and then fill storage tanks all over town. |
|
MERGER OF ASE WITH VWS ENVIG |
|
FLOOD RELIEF ASSISTANCE BY AQUA SERVICES & ENGINEERINGAqua Services & Engineering , the major Namibian supplier of water and wastewater treatment plant, equipment and chemicals, allocated N$ 25,000.00 to a fund to assist stricken employees and their families with the effects of the continuing floods. ASE conducted a survey to determine the requirements of its stricken employees and allocated N$ 8,500.00 for immediate relief to rebuild and repair housing structures. Furthermore N$ 16,500.00 has been allocated for food replenishment for the stricken families, which will be made available to the employees over the next few month to ensure the health of people, as most of their plantings have been destroyed by the floods, which would have served as their basic food source. Through this effort ASE will lighten the burden on the main relief program and ensure that dedicated relief reaches the stricken people. It is estimated that ASE will assist up to 100 people through this program. ASE can also design, build and make available mobile potable water treatment systems, within a short period to interested parties, which can provide potable water from any available raw water source. This enables ASE to provide potable water within a short time period to the effected regions where the main potable water supply network has been destroyed or is not functional. |
|
| Typical potable water treatment system for mobile application. |
|